Expressway marches past halfway point

The Hamilton section of the Waikato Expressway is halfway towards completion after two summer construction seasons, and the latest project video update is now available.

Around two million cubic metres of sand and soil were moved last summer and the expressway embankments have largely been constructed.

With the embankments out of the ground, earthworks can continue in winter, with the road pavement works starting in spring.

The Waikato Expressway will improve road safety, reduce journey times and congestion, and boost economic growth in the Waikato and across the country.

The Hamilton section is due to open in 2020. It will complete the 102km expressway that extends from the Auckland Motorway at Bombay to south of Cambridge.

Here’s the latest project video update from our friends at NZ Transport Agency:

SIGN UP GET THE E-NEWSLETTERSHARE
RELATED POSTS
Our City, Our Hamilton
Growth and Infrastructure Committee meeting wrap – 18 June 2019
First big consent for Peacocke
Concept drawings of the pedestrian overbridge for the Rotokauri Transport Hub
Construction to start on Rotokauri Transport Hub

Comments are closed.